Construction change order
CO-2026-0604
June 4, 2026 | contract CON-1847
Project and contractor
Cedar Point Tenant Buildout
742 Cedar Point Drive, Dayton, OH 45402
Contractor: Summit Field Construction
(555) 013-4490 | pm@summitfield.example
Client and reason
Harbor & Pike Properties
R. Collins | ownerrep@harborpike.example
Reason: Owner requested change
Requested by: Owner representative
Change reason and scope delta
Add backing and relocate rough-in for the breakroom sink after final cabinet layout changed. Includes selective drywall opening, blocking, plumbing relocation, patch-ready close-up, and coordination with cabinet installer.
Labor and material rows
| Type | Description | Qty | Unit | Unit cost | Total |
|---|---|---|---|---|---|
| Labor | Open drywall, install blocking, patch-ready close-up | 9 | hr | $84 | $756 |
| Labor | Plumbing rough-in relocation and pressure check | 6 | hr | $96 | $576 |
| Material | Blocking, fittings, supply line, drain parts, fasteners | 1 | allowance | $420 | $420 |
| Material | Drywall patch material and protection supplies | 1 | allowance | $165 | $165 |
Tax, markup, adjustment, schedule impact, and approval lines
Schedule impact: 2 days.
Extends substantial completion by 2 calendar days after owner approval.
Prepared by: M. Alvarez, Project Manager
Change order totals
Labor/material subtotal$1,917
Markup (12%)$230
Tax (7.25%)$42
Adjustment-$150
Total change$2,039